- REFERENCES AND RELATED POLICIES
-
UCSD Policy and Procedure Manual (PPM)
420-65 |
Minor Capital Improvements |
516-7.2 |
Environment, Health and Safety |
-
UC Facilities Manual - Volume 1, Chapter 4, Construction Contracts (pp.4-49)
-
Infopath
Capital Planning and Budgeting Home Page
Environment, Health and Safety Home Page
- BACKGROUND
The University is required to maintain strict controls over space and
equipment alterations. This requirement is to ensure that campus
facilities are fully used; alterations conform to applicable codes;
construction quality meets University standards; projects promote energy
conservation; and renovations are in the general interest of the
campus.
State law requires maximum use of outside contractors for
construction projects and limits the amount of in-house construction to
$50,000 for each project; however, painting or repainting projects are
limited to $25,000. These limits do not apply to experimental or
diagnostic equipment.
- POLICY
This policy does not apply to projects funded under formal
Universitywide State and non-State major capital programs and the
Universitywide State minor capital program.
- Project Review and Approval
All proposed changes to University-owned or University controlled
property and facilities regardless of the fund source of the original
facility or the proposed changes will be reviewed and approved by all
cognizant authorities before construction is started.
- Use of Work Request Form
A Work Request form is used to initiate all projects. For Campus
projects greater than $50,000 or Medical Center projects greater than
$20,000, use form FO2215 for Facilities Design and Construction (FD&C).
For Campus projects less than $50,000, use form FO2212 for Facilities Management (FM). For Medical Center projects less than $20,000,
use form FO2019 for Medical Center Facilities Engineering (MCFE.)
- Use of Renovations & Alterations (R&A) Form
A Renovations and Alterations (R&A) form, Exhibit A (also available
electronically on the Capital Planning & Budgeting home page), is used
to approve work which falls into any of the following categories:
- Cost estimated to be greater than $35,000.
- Change in space classification, e.g, from classroom to office,
seminar to laboratory, etc.
- Subdivision or enlargement.
- Any changes to external aesthetics.
- Change of space allocation from one department to another.
- Significant modifications to existing mechanical (HVAC and
plumbing) or electrical systems, as determined by FD&C, MCFE or FM.
- Installation/modification of any fire/life safety system (e.g.,
fire alarm/protection system, alterations/renovations affecting exiting,
etc.).
- Installation of carpeting (exception: carpeting being installed
when selected from the Environment, Health and Safety (EH&S) list of
pre-approved carpeting for installation as floor covering.)
- Installation of window coverings (exception: window coverings
being installed when selected from the EH&S pre-approved list.)
- Any work in leased properties.
- Work by FD&C, MCFE, or FM
MCFE or FM, or a licensed contractor under the direction of FD&C,
MCFE, or FM, will perform all construction/renovations/alterations of
University-owned or University-controlled buildings or installations of
equipment, including work done to utilities distribution systems, unless
an exception is approved under paragraph III.C.
Only FD&C, MCFE, or FM may make contracts or commitments with an
outside agency, vendor or contractor (including design professionals),
regardless of the size of the proposed project. Exception: Real Estate
Development is authorized to make contracts or commitments for buildings
it manages.
- Work by Other University Employees
- As an exception to usual policy, University employees
other than FD&C, MCFE, or FM may perform the work under the following
conditions:
- Requesting department receives prior written approval to do so from FD&C, MCFE, or FM before
construction begins,
- the construction is performed under FD&C, MCFE, or FM
inspection and supervision as determined upon obtaining approval
(including review of plans and EH&S consultation),
- the requesting department reimburses FD&C, MCFE, or FM
for the complete costs of supervision and inspection, and
- the requesting department is responsible for any liability or
damage resulting from construction by their faculty or staff employees.
- Approval will generally not be given if FD&C, MCFE, or FM
employees are available at the time to do the work. In these cases,
FD&C, MCFE, or FM assumes responsibility for getting the work done on a
timely basis by its own force or by contract.
- All work performed without the prior approval of FD&C, MCFE, or
FM is subject to removal or re-work to bring it into conformance with
all codes and the University's level of construction quality. Any
removal or re-work is at the expense of the department in whose space
the work was performed.
- Work on Leased Facilities
Renovations, repairs and alterations at leased facilities are subject
to requirements beyond those on campus, which may include obtaining City
of San Diego building permits, inspection by City building inspectors,
liability problems and compliance with City codes. It is in the
interest of the University that work at these locations be accomplished
by the lessor. Provisions for repairs and alterations are negotiated by
the Real Estate Development (RED) office.
If for any reason a renovation cannot be done by the lessor, written
permission must be obtained by RED from the lessor prior to commencement
of any work.
EH&S must review and approve plans for all alterations to University-
occupied space.
- PROCEDURE
-
Obtaining a Cost Estimate
-
Department completes the appropriate Work Request form containing
the following information:
- Clear
description of work.
- Rough sketch (not working drawing).
- Eligible fund source for recharging estimate and work to be
performed.
- Department forwards the Work Request and
other information to FD&C, MCFE, or FM.
- FD&C, MCFE, or FM reviews the proposed work, consults with E&HS
as necessary, and prepares a cost estimate. It also reviews the work to
determine if a R&A form is required.
- FD&C, MCFE, or
FM returns a copy of the Work Request with a signed estimate, or a memo
quoting estimated cost to the originating department.
- Using a Work Request Form Only
If a department wishes to proceed with the work based on the cost
estimate and a R&A form is not required, the department authorizes FD&C,
MCFE, or FM to proceed.
- Using a Renovations & Alterations (R&A) Form/b/p
- If a R&A form is required under Paragraph III.A.2,
department prepares the R&A form, attaches the cost estimate and any
background information, and obtains the approval and signature of the
department head.
- After approval by the department head, the package is routed to
the following offices:
-
Applicable Dean, Director, or Provost
- Capital Planning & Budgeting (CP&B)
- . Environment, Health and Safety (EH&S)
- Facilities Design and Construction, Medical Center Facilities
Engineering, or Facilities Management
- Real Estate Development, for projects in leased space or
buildings managed by RED
Any of the above offices
that do not grant approval will notify CP&B.
- Work Under $35,000
If work is under $35,000 and all approvals have been given, FD&C,
MCFE, or FM will proceed with the work, if the following conditions are
met: - Work is
to done by FD&C, MCFE, or FM,
- Originating department has made funds available, and
- Originating department has given its approval to proceed.
- Work Over $35,000
A project with costs greater than $35,000, but less than $750,000 is
considered part of the State or Non-State Minor Capital Improvement
Program. See PPM 420-65 for additional policies and procedures
regarding projects that meet these conditions.
- Master Files
CP&B maintains master files of R&As covering work accomplished.
EXHIBIT A
REQUEST FOR RENOVATIONS AND ALTERATIONS (R&A)
- ORIGINATING DEPARTMENT
Department Name/VC Area ______________________________________________________
Originator __________________Signature______________________Date_________________
Work Contact_________________Phone___________E-mail_________Mail Code__________
- PROJECT DESCRIPTION
Description of work to be done (attach sketch or floor plan)___________________________ __________________________________________________________________________ __________________________________________________________________________
Building Name or Number_________________Room Number(s)________________________
Assignable Square Feet (project area, and only if applicable)___________________________
Is this leased space? Y N If Yes, indicate address_____________________________________
FD&C Job Number or FM Work Order Number__________Estimated Cost_______________
FD&C/FM Project Manager Name_______________________________________________
- SOURCE OF FUNDS
Proposed fund source name______________________________________________________
Index________Fund__________Organization________Program________Account___________
(note: for use of 19900 funds see note on back)
Will Federal Funds be used to fund any part of this project? Y N
Will equipment purchased with Federal Funds be installed as part of this project? Y N
Plant Organization number(established by CP&B)______________________________________
- APPROVALS
(route one copy only)
In the following order:
Department Head_________________________________________Date__________________
Director or Dean___________________ ______________________Date__________________
Capital Planning & Budgeting (0915)___________________________Date_________________
Environment Health & Safety (0920)
- Preliminary(*)_______________________________________Date_________________
- Final______________________________________________Date_________________
Facilities Design & Construction (0916)
- or Facilities Management (0908)
- or Medical Center Facilities Engineering (8206)_______________Date_______________
For Leased Space Only:
UCSDMC Facilities Planning & Management (8861)_________________Date_______________
(Medical Center projects only)
Real Estate Development (0982)________________________________Date______________
(general campus, SOM, SIO, and UCSDMC after approval by UCSDMC Facilities Planning and Mgmt.)
(*)budgeting purposes only as final plan review and approval is required
Return signed form to Capital Planning and Budgeting (0915)
EXHIBIT B
USE OF RENOVATIONS AND ALTERATIONS (R&A) FORM
The purpose of the Request for Renovations and Alterations (R&A) form is to inform and obtain approvals from necessary administrative offices of proposed construction, renovations or alterations to University owned or University controlled property and facilities, including leased facilities. The R&A form is used when work is funded from any source except the Major Capital Improvement Program and the State Minor Capital Improvement Program. Refer to related PPMs 420-65, 530-9, and 516-7.2.
Use of 19900 funds Up to $35,000 of 19900 funds can be used provided that the project does not result in a capital improvement project. If the project does result in a capital improvement project, 19900 funds cannot be transferred to plant funds.
Minor Capital Improvement Project Minor capital improvements are defined as projects that add new space or alter the programmed design or function of space or building systems, including related fixed equipment, and utility and site development improvements.
A R&A form is required for work falling into any one of the following categories:
- Cost estimated to be greater than $35,000.
- Change in space classification, e.g., from classroom to office, seminar to laboratory, etc.
- Subdivision or enlargement.
- Any change to external aesthetics.
- Change of space allocation from one department to another.
- Modifications to existing mechanical (HVAC and plumbing) or electrical systems.
- Installation/modification of any fire/life safety system (e.g., fire alarm system, fire protection system, alterations/renovations affecting exiting, etc.)
- Installation of carpeting (Note: a R&A form is not required if carpeting is selected from the Environment, Health and Safety office list of pre-approved materials and applications and if the project is less than $35,000. See EH&S Web Page: www-vcba.ucsd.edu/ehs/home.htm)
- Installation of window coverings.
- Any work in leased properties.
All work must be managed by Facilities Design & Construction (FD&C) or Facilities Management (FM) through submission of a R&A form. See Para. III.B., PPM 530-9 for policy regarding the management and inspection of the work.
Signed forms will be archived by Capital Planning & Budgeting.
| |